ONLY TWO DECK-SEGMENTS LEFT FOR THE WIDENING OF RANDE BRIDGE

10/2017

The Widening of Rande Bridge in Pontevedra approaches its completion, as there are only two more deck-segments to be lifted and installed. These remaining 17-meter long deck-segments are the closing ones at the center of the 400-meter main span. After that, the last main operation is the adjustment of the loads for all the new cables.

It’s great to see how all these months of hard work finally start paying off and the bridge is really close to taking its final shape. FHECOR is part of the Construction Engineering team, along with PONDIO, providing technical assistance to the CJV composed of Dragados and Grupo Puentes.